ROAD WORK CONTINUES FOR WATERMAIN
Release Date: April 29, 2020

A watermain replacement project began on May 11, 2020.

The project will start at West 76th Street and the Boulevard and will continue north to West 80th Street in the southbound lane of the Boulevard.

Anticipated work is scheduled to begin on May 11th and completed on May 29th for pipe installation.

Final paving to be completed no later than June 19th.

All work to be done will be weather dependent.

Work hours will typically be 7:30AM to 3:30PM, Monday through Friday.

Approximately 50 feet of roadway trench will be open at any given time during the construction day.

Click here to view an aerial map of the project area and time schedule.