(Click on picture for larger view)
Click here for Photo Album by street11/30/09 - Project continues at 80th Street:
11/29/09 - Project continues - ramp removed:
11/27/09 - Project continues:
11/26/09 - Project continues:
11/25/09 - Project continues between 76th and 77th Streets:
11/23/09 - Project delayed due to northeast winds and 10' swells.
11/22/09 - Project continues between 76th and 77th Streets:
11/21/09 - Project continues between 76th and 77th Streets:
11/20/09 - Project view from Atlantic Ocean:
11/20/09 - Project continues between 76th and 77th Streets:
11/19/09 - Project continues between 76th and 77th Streets:
11/18/09 - Project continues between 76th and 77th Streets:
11/17/09 - Project begins Tuesday morning November 17, 2009 between 76th and 77th Streets:
11/11/09 - Storm conditions (nor'easter from remnants of Hurricane IDA) - project delayed.
11/10/09 - Initial (test) sand pumping between 76th and 77th Streets:
11/10/09 - Setting up the pipeline:
What is being done and where?
How long will it take?
Who is involved?
How much will it cost?
For more information…
The Harvey Cedars portion of the Long Beach Island Beachfill Project will begin construction in October.
Once started, work will be conducted 24 hours a day, 7 days a week until project completion.
The contractor will be pumping sand from a set location in the ocean through a screen to a hopper dredge, then through a smaller diameter screen onto the beach via a 36-inch diameter pipeline. The project will begin at the north end of Harvey Cedars and continue south.
Once on the beach, heavy equipment will move the sand to its proper position. Throughout the project there will be areas of the beachfront occupied by construction vehicles, pipeline, and other necessary equipment. It is anticipated that approximately 1,000 feet of beachfront will be closed to public access at any one time for safety reasons, as the beach is being built at a rate of 100 – 200 linear feet per day.
Representatives from the DEP, Army Corps of Engineers and the contractor will be available at our next regular Commissioner’s meeting on October 20th at 4:30pm to answer questions regarding this project.